New Construction Progress

A momentous decision was made that marks a new chapter for our church community. With an overwhelming approval, a motion to move forward with the plans to build a new social hall, complete with a children's wing and preschool area has officially passed! This is more than just a building; it's a promise to our future, a commitment to fostering connections, and a space where our children can grow, learn, and play. Together, we are building more than walls; we are creating a home for Christian community and fostering worship and fellowship.
A huge thank you to everyone who participated, provided testimony, and made their voices heard. This is a God-sized project that can only be accomplished by trusting in Jesus Christ. May we move forward in faith and follow Him in all we do!
Update June 5, 2025:
Children's Wing & Social Hall Construction Update
We have exciting news to share about the new Children's Wing and Social Hall!
Trehel Corporation Inc. reports significant progress:
Engineering drawings were completed May 30.
Architect David McAbee is now reviewing and coordinating these drawings, with engineers making any necessary adjustments.
Trehel anticipates having the "Issue for Permit Set" of drawings by June 20th. At that point, they'll be ready to submit for permits and begin preparing the final cost estimate for the project.
The estimation process will take several weeks. Permit review times are determined by local authorities, but we expect it to take one to two months. We're happy to report that after some initial delays, the project is now moving forward at a good pace!
Your continued generosity to the Sacrifice to Build Program is vital to funding this new building. If you haven't already, please consider giving to support this important endeavor.
A huge thank you to everyone who participated, provided testimony, and made their voices heard. This is a God-sized project that can only be accomplished by trusting in Jesus Christ. May we move forward in faith and follow Him in all we do!
Update June 5, 2025:
Children's Wing & Social Hall Construction Update
We have exciting news to share about the new Children's Wing and Social Hall!
Trehel Corporation Inc. reports significant progress:
Engineering drawings were completed May 30.
Architect David McAbee is now reviewing and coordinating these drawings, with engineers making any necessary adjustments.
Trehel anticipates having the "Issue for Permit Set" of drawings by June 20th. At that point, they'll be ready to submit for permits and begin preparing the final cost estimate for the project.
The estimation process will take several weeks. Permit review times are determined by local authorities, but we expect it to take one to two months. We're happy to report that after some initial delays, the project is now moving forward at a good pace!
Your continued generosity to the Sacrifice to Build Program is vital to funding this new building. If you haven't already, please consider giving to support this important endeavor.